When cloning an existing schedule day after changing Start/End location from user settings and toggles ON the Clone Start and End location, it throws an error [Upsert failed. First exception on row 0; first error: REQUIRED_FIELD_MISSING, Required fields are missing: [Resource Id]: [Resource Id] - (maps)]

Repro
Found in SF Maps v232.7.3
navigate to schedule
update the start or end location's address for a day
save the schedule
clone the schedule (with clone start/end locations activated)

Workaround
Clone the Schedule day by keeping Toggle off (Clone Start and End Locations) and then manually update the Start End location of cloned schedule day